Bill of Materials and Production Costing: Finding the True Cost of a Finished Product

The true cost of a finished product is its bill of materials cost plus the direct labour and the share of production overheads it uses, with materials costed including expected waste. The bill of materials alone can leave out a fifth or more of the real cost, so pricing from it overstates margin.

Factory worker with a clipboard beside production machinery

Frequently asked questions

What is the difference between a BOM and a routing?

A BOM lists the materials and components in a product. A routing lists the operations, work centres and times needed to make it. Together they give material, labour and machine cost.

Can factory rent be included in product cost?

Yes. Under IAS 2, fixed production overheads such as factory rent and depreciation are part of product cost, allocated on normal production capacity. Head office rent and other administration costs are not.

What is normal capacity?

The production a factory expects to achieve on average over several periods under normal conditions, after allowing for planned maintenance. It is used to set the fixed overhead rate, so the rate doesn't rise in slow months.

How are by-products costed?

IAS 2 allows by-products that are immaterial to be measured at net realisable value, with that amount deducted from the cost of the main product. Joint products are allocated costs on a rational and consistent basis, such as relative sales value.

How often should standard costs be updated?

At least once a year, and whenever a major material price, wage rate or process changes. IAS 2 allows standard costs for valuation only if they approximate actual cost and are reviewed regularly.