Subcontractor Payment Certificates: Tracking Retention, Advances and Deductions

A subcontractor payment certificate states how much the main contractor owes a subcontractor for work done to date. Start from the cumulative value of work, approved variation orders and materials on site, deduct retention, advance payment recovery and contra-charges, then subtract what was certified before. The difference is this period's certified amount. The payment is that amount plus VAT on the subcontractor's invoice, less the VAT on any contra-charges, which are invoiced separately.

Two site engineers in hard hats reviewing a document

Frequently asked questions

What is retention in a subcontract?

A percentage of each certified amount held back by the main contractor as security against defects, usually released in two halves: at completion and after the defects liability period.

How is an advance payment recovered?

By deducting an agreed percentage from each certificate until the full advance is repaid. The advance payment guarantee reduces as the advance is recovered.

Why use cumulative figures on a payment certificate?

Because retention, advance recovery and previous payments are then calculated on the total to date, which corrects any earlier error automatically.

Can unapproved variations be included?

No. List them separately as pending until they are approved, then add them to the next certificate.

What is a contra-charge?

A cost the main contractor paid on the subcontractor's behalf, such as utilities, scaffolding or rework, deducted from a certificate with supporting evidence.